Preliminary dredging will take place in the harbor entrance on March 22. The dredging should only take one day. We will return with information about possible closure of the harbor entrance in connection with the dredging.
Tentatively, stone will begin to be delivered to the fenced stockpile at the E-on pump house on the western side of the harbor entrance during Easter week.