Information from JM regarding the construction of Docks!

22 Dec, 2021

Hello!

Here is some information on what will happen at the beginning of next year at the construction of Docks.

Minor work will take place v.52, but no noisy work.

some demolition and sheet piling will continue.
most of them are back and the work continues with sheet piling and shafts.
we will plan to carry out the traffic diversion. We will also perform a test pile with 4-5 piles during v.2-3.
The sheet piling work is expected to be completed in v. 6, which we understand will be nice as there is a lot of noise.

We hope you all have a Merry Christmas and a Happy New Year.

With kind regards

Management team Docks